Veolia needed to strengthen backup power at its Třebovice power plant in Ostrava with high power density in a limited footprint.
A TWIN configuration (two engines in one unit) was meant to maximize installed power without requiring additional footprint.
Solutions
Solution
We delivered 7 Fogo FD 1320ST diesel generator units in TWIN configuration, i.e. with a total of 14 engines, with a total installed power of 7.238 MW.
The TWIN configuration made it possible to achieve high power on the compact footprint of the Třebovice power plant.
Results
The numbers after implementation.
7,238 MW
Total installed power
14
Engines (7× TWIN)
2024
Year of commissioning